    Moin

    ich bräuchte die Anzugsdrehmomente für die Kopfschrauben vom 2,5l SP mit Reihenfolge.

    Wäre super mir einer helfen könnte.

    Gruß Tom
     
  2. #2 samse2101, 15.06.2014
    samse2101

    samse2101 Guest

    INSTALLATION
    The engine cylinder head gasket is a composition
    gasket. The gasket is to be installed DRY. DO NOT
    use a gasket sealing compound on the gasket.
    If the engine cylinder head is to be replaced and
    the original valves used, measure the valve stem diameter.
    Only standard size valves can be used with a
    service replacement engine cylinder head unless the
    replacement head valve stem guide bores are reamed
    to accommodate oversize valve stems. Remove all
    carbon buildup and reface the valves.

    (1) Fabricate two engine cylinder head alignment
    dowels from used head bolts (Picture 1). Use the longest
    head bolt. Cut the head of the bolt off below the hex
    head. Then cut a slot in the top of the dowel to allow
    easier removal with a screwdriver.

    [​IMG]

    (2) Install one dowel in bolt hole No.10 and the
    other dowel in bolt hole No.8 (Picture 2).

    [​IMG]

    (3) Remove the shop towels from the cylinder
    bores. Coat the bores with clean engine oil.

    (4) Place the engine cylinder head gasket (with the
    numbers facing up) over the dowels.

    (5) Place the engine cylinder head over the dowels.

    CAUTION: Engine cylinder head bolts should be reused
    only once. Replace the head bolts if they were
    used before or if they have a paint dab on the top
    of the bolt.


    (6) Coat the threads of bolt No.7, only, with Loctite
    PST sealant or equivalent.

    (7) Install all head bolts, except No.8 and No.10.

    (8) Remove the dowels.

    (9) Install No.8 and No.10 head bolts.

    (10) Tighten the engine cylinder head bolts in sequence
    according to the following procedure (Fig. 6):
    (a) Tighten all bolts in sequence (1 through 10)
    to 30 Nm (22 ft. lbs.) torque.
    (b) Tighten all bolts in sequence (1 through 10)
    to 61 Nm (45 ft. lbs.) torque.
    (c) Check all bolts to verify they are set to 61
    Nm (45 ft. lbs.) torque.
    (d) Tighten bolts (in sequence):
    -> Bolts 1 through 6 to 149 Nm (110 ft. lbs.) torque.
    -> Bolt 7 to 136 Nm (100 ft. lbs.) torque.
    -> Bolts 8 through 10 to 149 Nm (110 ft. lbs.) torque.

    CAUTION: During the final tightening sequence,
    bolt No.7 will be tightened to a lower torque than
    the rest of the bolts. DO NOT overtighten bolt No.7.


    (e) Check all bolts in sequence to verify the correct
    torque.
    (f) If not already done, clean and mark each bolt
    with a dab of paint after tightening. Should you
    encounter bolts which were painted in an earlier
    service operation, replace them.

    [​IMG]

    (11) Install the ignition coil and bracket assembly.

    (12) Connect the temperature sending unit wire
    connector.

    (13) Install the spark plugs and tighten to 37 Nm
    (27 ft. lbs.) torque. Connect the ignition wires.

    (14) Install the intake and exhaust manifolds (refer
    to Group 11, Exhaust System and Intake Manifold
    for the proper procedures).

    (15) Install the fuel lines and the vacuum advance
    hose.

    (16) If equipped, attach the power steering pump
    and bracket.

    (17) Install the push rods, rocker arms, pivots and
    bridges in the order they were removed.

    (18) Install the engine cylinder head cover.

    (19) Attach the air conditioning compressor mounting
    bracket to the engine cylinder head and block.
    Tighten the bolts to 40 Nm (30 ft. lbs.) torque.

    (20) Attach the air conditioning compressor to the
    bracket. Tighten the bolts to 27 Nm (20 ft. lbs.)
    torque.

    CAUTION: The serpentine drive belt must be routed
    correctly. Incorrect routing can cause the water
    pump to turn in the opposite direction causing the
    engine to overheat.


    (21) Install the serpentine drive belt and correctly
    tension the belt.

    (22) Install the air cleaner and ducting.

    (23) Install the engine cylinder head cover.

    (24) Connect the hoses to the thermostat housing
    and fill the cooling system to the specified level.

    (25) The automatic transmission throttle linkage
    and cable must be adjusted after completing the engine
    cylinder head installation.

    (26) Install the temperature sending unit and connect
    the wire connector.

    (27) Connect the fuel pipe and vacuum advance
    hose.

    (28) Connect negative cable to battery.

    (29) Connect the upper radiator hose and heater
    hose at the thermostat housing.

    (30) Fill the cooling system. Check for leaks.

    WARNING: USE EXTREME CAUTION WHEN THE
    ENGINE IS OPERATING. DO NOT STAND IN DIRECT
    LINE WITH THE FAN. DO NOT PUT HANDS NEAR
    THE PULLEYS, BELTS OR FAN. DO NOT WEAR
    LOOSE CLOTHING.


    (31) Operate the engine with the radiator cap off.
    Inspect for leaks and continue operating the engine
    until the thermostat opens. Add coolant, if required.
     